2025 Winter Break IT Updates

IT Service Desk image

December 22 - January 9 Winter Break IT Updates

Holiday Greetings to our SPC Colleagues!

As the semester winds down, the IT & IR projects ramp up! While we hope to have all our projects done before faculty and students return, we will prioritize classroom, semester start and security tasks first. Please see the list below for our Spring Semester Readiness tasks, the impact, and potential downtime or end-user impacts. As always, please contact the Service Desk if you have questions.

IT/IR Spring Semester Readiness Tasks
# Task Name Dates Group Responsible Information Status
1 Adobe Account Cleanup 12/22 - 1/9 Service Desk Remove/Add DGIM Students & Audit Employee Accounts Completed
2 Computer Lab/Classroom Cleanup 12/22 - 1/9 Service Desk Wipe down the instructor station/student computers Completed
3 AV Readiness 12/22 - 1/9 AV Team Ensure AV connections and functions are working. Completed
4 Prep Student Loaners for Spring 12/22 - 1/2 Service Desk Prepare Student loaner devices, communicate, and schedule. Completed
5 Update Service Portal and update forms & KB 12/22 - 1/31 All IT

Update Service Portal, convert generic service forms; focus on updating new forms; review KBs for accuracy

Match information on SPC IT Service Page (requires updates with Marketing)

In progress
6 Printer Copier maintenance 12/22 - 1/9 Vendor Perform preventative maintenance on all copiers and printers In progress
7 Ticket Cleanup 12/22 - 1/9 All IT Review all tickets and close tickets as needed In progress
8 Computer Updates 12/22 - 1/9 All IT

Perform security and operating system audits and updates

  • Update computer labs to 25H2 (requires extended reboot time); need to schedule communication to employees
  • Update Ivanti Security Control to Ivanti Neurons for improved computer patching
  • Updating startup and shutdown scripts on student devices
  • Ensure all devices are maintained with consistent software patch levels
In progress
9 Phone Updates 12/24 & 12/26 Network Team Run firmware updates on physical phones; requires a phone reboot, which will affect the internet via docking stations. Expected downtime ~ 5 minutes per workstation or docking station. Completed
10 Specialized Software Location Review 12/22 - 1/7 Service Desk Audit specialized software locations to ensure the correct software is installed in the correct location for the start of the semester Completed
11 Security Certs (SSL) Updates 12/24 & 12/26 Network Team

Security cert updates on all servers, including PaperCut (12/26).

  • PaperCut complete
  • Web servers complete
  • VPN, VDI, Alterus - complete
Major certs completed; minor in progress
12 Lenel/Milestone Public Safety Device Swap 1/5 Network/Service Desk Scheduled device replacement. (rescheduled 1/5/2026) Scheduled
13 VDI Image Update 12/22 - 1/7 Network/Service Desk Update VDI Image for Students and Staff in preparation for the Spring Semester. In progress
14 Dashboards & Paginated Report Updates 12/22 - 1/9 Data Services/IR Update reports as the semester starts; some data will be updated after the start, due to event timing. Scheduled
15 RedShelf --> VitalSource Conversion (D2L) Completed Service Desk VitalSource has been implemented, and instructors/faculty need to update their D2L courses to point to VitalSource if they were using RedShelf. Completed

 